1. Business Requirements Alignment

Timeframe: 1–3 Days*(Needs input as of 12/9/24)

  • Step 1: Business Requirement Alignment and Preliminary Analysis

    • Timeframe: 1–2 days*(Needs input as of 12/9/24)

    • Purpose:

      • Meet with stakeholders to identify high-level business goals, assess alignment with strategic priorities, and conduct back-of-the-napkin calculations.

      • Evaluate initial cost, risk, and benefit to determine if the effort aligns with company priorities and constraints.

    • Output:

      • Initial business case with rough calculations to justify further discovery and planning.

  • Step 2: Business Risk/Cost/Benefit Assessment (Post-PRD)

    • Timeframe: 1 day*(Needs input as of 12/9/24)

    • Purpose:

      • After the PRD is finalized, conduct a more detailed assessment of cost, risks, and benefits using the requirements and LOE estimates.

      • Provide an updated recommendation to proceed or reevaluate based on feasibility and potential ROI.

    • Output:

      • Detailed business case to support the next steps in the process.

2. Requirement Gathering Process

Timeframe: 1.25 - 2.25 Weeks

  • Step 1: Stakeholder Alignment

    • Timeframe: 1–2 days

    • Purpose:

      • Meet with stakeholders (product, engineering, integrations) to understand high-level goals and prioritize features.

    • Output:

      • Initial list of requirements, prioritized based on impact and feasibility.

  • Step 2: Discovery and Research

    • Timeframe: 1–2 weeks (depending on complexity)

    • Purpose:

      • Conduct research, gather input, analyze existing data, and review constraints.

    • Output:

      • Refined list of requirements with supporting data, initial technical considerations, and key dependencies identified.

3. PRD Development

Timeframe: 3 - 4 Weeks

  • Step 1: Initial Draft

    • Timeframe: 1 week

    • Purpose:

      • Write the initial PRD with high-level requirements and user stories.

      • Collaborate with engineering to identify potential challenges, key dependencies, and scope.

    • Output:

      • Draft PRD ready for review.

  • Step 2: Wireframe Creation

    • Timeframe: 3–5 days (overlapping or sequential with Step 1, as needed)

    • Purpose:

      • Create wireframes to visually represent key workflows, user interactions, and page layouts.

      • Ensure alignment between product vision, engineering feasibility, and UI/UX requirements.

    • Output:

      • Wireframes included in the PRD for context and reference during estimation.

  • Step 3: LOE and High-Level Design Review

    • Timeframe: 1–1.5 weeks

    • Purpose:

      • Collaborate with engineering to refine requirements.

      • Create a high-level design and task breakdown.

      • Estimate the Level of Effort (LOE) for development, integration, and testing.

    • Output:

      • Updated PRD with detailed LOE estimates, risks, and dependencies.

      • High-level design and task breakdown.

  • Step 4: Timeline and Milestone Planning

    • Timeframe: 2–3 days

    • Purpose:

      • Define a development timeline based on LOE, factoring in dependencies and resource availability.

      • Incorporate milestones into the PRD.

    • Output:

      • Finalized PRD with requirements, wireframes, LOE, timelines, and milestones.

4. Jira Ticket Creation and Task Breakdown

Timeframe: 1–3 Days

  • Purpose:

    • Engineering creates Jira tickets based on PRD requirements and the implementation plan.

    • Ensure tasks are actionable and aligned with the roadmap and PRD deliverables.

  • Output:

    • Jira tickets with clear requirements, task ownership, and dependencies, ready for sprint planning and execution.

5. UX/UI Design (Figma Design)

Timeframe: 1-2 weeks

  • Purpose:

    • Use PRD requirements (and possible wireframes) to develop Figma designs and prototypes.

    • Collaborate with engineering and UI/UX Design team to identify potential challenges, key dependencies, and scope.

  • Output:

    • Figma Design ready for review.


Requirements Planning Framework (2).png
@startgantt

' Business Requirements Alignment Phase
[Business Requirements Alignment] lasts 3 days and is colored in #lightgray
[Business Requirement Alignment and Preliminary Analysis] lasts 2 days and is colored in #lightgray
[Business Requirement Alignment and Preliminary Analysis] -> [Requirements Gathering]

' Requirements Gathering Phase
[Requirements Gathering] lasts 12 days and is colored in #lightblue
[Stakeholder Alignment] lasts 2 days and is colored in #lightblue and starts at [Requirements Gathering]'s start
[Discovery and Research] lasts 10 days and is colored in #lightblue
[Stakeholder Alignment] -> [Discovery and Research]

' PRD Development Phase
[PRD Development] lasts 16 days and is colored in #lightgreen
[Requirements Gathering] -> [PRD Development]
[Initial Draft] lasts 5 days and is colored in #lightgreen
[Wireframe Creation] lasts 5 days and is colored in #lightgreen
[LOE and High-Level Design Review] lasts 8 days and is colored in #lightgreen
[Timeline and Milestone Planning] lasts 3 days and is colored in #lightgreen
[Discovery and Research] -> [Initial Draft]
[Initial Draft] -> [Wireframe Creation]
[Wireframe Creation] -> [LOE and High-Level Design Review]
[LOE and High-Level Design Review] -> [Timeline and Milestone Planning]

' Post-PRD Business Analysis Phase
[Post-PRD Business Analysis] lasts 1 day and is colored in #lightgray
[Timeline and Milestone Planning] -> [Post-PRD Business Analysis]

' Jira Ticket Creation Phase
[Jira Ticket Creation] lasts 3 days and is colored in #lightcoral
[Timeline and Milestone Planning] -> [Jira Ticket Creation]

' UX/UI Design Phase
[UX/UI Design (Figma Design)] lasts 2 weeks and is colored in #orange
[Timeline and Milestone Planning] -> [UX/UI Design (Figma Design)]


@endgantt

https://UCFNextgen.ai/public/plantuml/1055